Our project highlights

For a list of SENET's projects, see below

SENET has executed some unique studies and projects throughout Africa and the world, and in the process gained valuable knowledge which it applies towards guaranteeing the success of new projects, and completing future studies with increased efficiencies and reduced schedules.

worldwide

"Portfolio of projects WORLDWIDE"
Unique Features:

First Gold Heap Leach Plant carried out by a South African Company.

Unique Features:

First process plant to be erected in Eritrea.

Unique Features:

Incorporated SENET proprietary equipment for Heap Leach Stacking.

Unique Features:

Longline Conveyor Protection

Unique Features:

41 off 40m Gantry bridges for land assembly and barge placement 220m curved conveyor to eliminate an additional transfer point and conveyor

Unique Features:

Blasting of the 70m by 30m deep cave

Unique Features:

R.O.M bin had a side tip arrangement with an inclined, self cleaning grizzly

Unique Features:

The largest circular flotation plant in Southern Africa, with 18 X 130m tank cells with 160kW motors

Unique Features:

Crushing, Agglomeration and Stacking Equipment.

Unique Features:

Crushing, scrubbing, milling, leach, CIP elution, electrowinning and gold smelting, 12 kilometres of overland pipelines for raw water, tailings, return water and process water

Unique Features:

100,000 ton Mass Flow Hoppers and Belt Feeders

Unique Features:

Dry tailings due to water shortage in the area

Unique Features:

First plant in RSA to use circular flotation cells and the plant was designed to minimise operating staff

Unique Features:

Drums required FEA and Dynamic Analysis, and special retaining devices and structures due to seismic conditions

Unique Features:

Specialised Chute Design and Test Work for 90 degree transfer points.

Unique Features:

Skid mounted grasshopper conveyors

Unique Features:

Completed on time within budget

Unique Features:

Incorporated SENET proprietary equipment for heap leach, i.e. cement handling, agglomeration drum and complete stacking system

Unique Features:

Incorporated SENET proprietary equipment for heap leach, i.e. cement handling, agglomeration drum and complete stacking system

Unique Features:

Crushing, scrubbing, milling, leach, CIP, elution, electrowinning and gold smelting

Unique Features:

The Design & Engineering is 3D Model based with interfacing with other Suppliers being the major challenge.

Unique Features:

Hydraulic gull wing slewing wheels

Unique Features:

Process building incorporating, 7 Disc Filters, 6 Low Intensity Magnetic Separators, 6 Vacuum Pumps, Cooling plant

Unique Features:

80 000 tons per month

Unique Features:

Crushing, scrubbing, milling, leach, CIP elution, electrowinning and gold smelting

Unique Features:

The project is in the middle of the Sahara desert which made the construction and erection a very challenging task

Unique Features:

The project is in the middle of the Sahara desert which made the construction and erection a very challenging task.

Unique Features:

Skid mounted grasshopper conveyors

Unique Features:

The largest grasshopper type heap leach stacking system regarding tonnage

Unique Features:

Remote location in mountains of the North of the DRC.

Unique Features:

Extreme temperature variation – minus 45 to plus 45 Celsius

Unique Features:

SENET proprietary equipment for heap leach, i.e. cement handling, agglomeration drum and complete stacking system.

Unique Features:

Fully Automated, Hydraulically Self Driven/Steering, Crawler mounted Tripper c/w luffing cross conveyor which luffs between a discharge height of 4 to 12m

Unique Features:

Fully Automated, Hydraulically Self Driven/Steering, Crawler mounted Tripper c/w luffing cross conveyor which luffs between a discharge height of 4 to 12m

Unique Features:

Fully Automated, Hydraulically Self Driven/ Steering, Crawler mounted Tripper c/w luffing cross conveyor which luffs between a discharge height of 4 to 12m