SENET, a DRA Global company, has completed the bulk-earthworks on the Tri-K Gold Project, located in the Mandiana region of the Republic of Guinea, West Africa.

The project was awarded to SENET in 2019 following the successful completion of the Definitive Feasibility Study (DFS).

The progress made on the project, achieved despite the challenges of a global pandemic, has seen some 23 000 m3 of excavations, 162 000 m3 of imported fill and the construction of a 15m-high mechanically stabilized earth ROM wall.

Suggested Articles

06 Jul 2020
SENET resumes Detailed Feasibility Study activities for Kiniero Gold

Following initial work on an early PFS technical report in Q1 2020, SENET resumes detailed Feasibility Study (FS) act... Read More

01 Jul 2020
SENET achieves significant bulk-earthworks milestone on Tri-K Project

SENET, a DRA Global company, has completed the bulk-earthworks on the Tri-K Gold Project, located in the Mandiana reg... Read More

15 May 2020
SENET: Definitive Feasibility Study for the Rovina Valley Project

SENET, a DRA Global group company, has been awarded the contract for the Definitive Feasibility Study (FS) for the Ro... Read More